Exchange Received Time  09/03/2017 13:14:05 Exchange Disseminated Time 09/03/2017 13:14:13 Time Taken 00:00:08 | REVISED - DBL Hata Dargawon Tollways Limited (a SPV of the Company) has received the provisional Completion certificate as declaration of Commercial Operation Date (COD) for the Project of 'Development of the Hata-Fatehpur-Rajpura-Silapuri-Bajna-Dargawon"(Km 0+000 to Km 64+230) of State Highway No. 48 on design, Build, Finance, operate & transfer(DBFOT) on (Toll+Annuity) basis and the project cost 101.09 Crore. Further, as per the said Certificate, the said project is completed 400 days prior to the schedule Completion date and in lieu of the earlier completion of the Project, Company is entitled to received maximum Bonus amount Rs.15,38,63,013/- from the Madhya Pradesh Road Development Corporation Limited and provisionally declared fit for entry into Commercial operation dated 06th March, 2017. The trading window for dealing in the securities of the Company by its designated employees, directors and promoters shall be closed from 09.032017 to 14.03.2017(both days inclusive). |
|
|