Exchange Received Time  22/01/2018 08:26:21 Exchange Disseminated Time 22/01/2018 08:26:27 Time Taken 00:00:06 | The Company had earlier intimated vide letter dated July 28, 2017 that it has emerged as the lowest bidder for Construction, Operation And Maintenance of 2-Lane Bi-Directional Zojila Tunnel with Parallel Escape (Egress) Tunnel on Srinagar-Leh Section (the 'Project') in the State of Jammu & Kashmir on EPC mode at a cost of ? 4899.42 Crore. The Project is implemented by Ministry of Road Transport & Highways ('MORTH') through National Highways & Infrastructure Development Corporation Limited ("NHIDCL") We wish to inform that the Company has received a Letter of Acceptance dated January 19, 2018 from NHIDCL for development of the Project. The construction period for the Project is 2555 days |
|
|