Exchange Received Time  12/05/2017 18:11:46 Exchange Disseminated Time 12/05/2017 18:11:53 Time Taken 00:00:07 | Pursuant to Regulation 30 of the Listing Regulations, vide our letter dated 18th July, 2016, we had informed you about the Company agreeing to acquire the 500 MW (2X250 MW) thermal power plant located at Bina, District Sagar in the State of Madhya Pradesh from Jaiprakash Power Ventures Limited with 31st May, 2017 (the Long Stop date) as the indicative time period for completion of the acquisition. We now wish to inform you that, as mutually agreed between the parties, the Long Stop date has been extended to 31st December, 2017. All other terms and conditions remain unchanged. The above is for your kind information and record. |
|
|