Exchange Received Time  18/10/2017 10:52:33 Exchange Disseminated Time 18/10/2017 10:52:38 Time Taken 00:00:05 | We are pleased to inform you that the Company has received the Provisional Completion Certificates, prior to the Scheduled Completion Date for the Project 'Rehabilitation and Up-gradation of Mandla-Chilpi Section of NH-12A from existing Km. 89/500 to 192/4 including construction of Mandla, Madhopur and Anjania bypass in the State of Madhya Pradesh to two lane with paved shoulders on EPC Mode under NHDP-IV' and consequently the Company is entitled to a maximum bonus amount of Rs.12,45,24,000/- in lieu of earlier completion of the said Project. |
|
|