With reference to the earlier letter dated April 11, 2016 informed that it has signed an MOU with Sanjana Cryogenics Storage Ltd (SCSL), its Ammonia Terminal Operator, for re-routing a portion of the ammonia pipeline that runs from the Haldia Dock to the Ammonia Storage tank. This has been done at the directive of Kolkata Port Trust for facilitating the set up a Multi-Modal Terminal Hub at Haldia by Inland Waterways Authority of India (IWAI).

Tata Chemicals Ltd has now informed BSE that pipeline re-routing activity was likely to cause a shutdown of operations by about 5 weeks in September-October, 2016 due to interruption of ammonia supply to the TCL-Haldia phosphatic fertiliser plant.

In this regard, as per the current project status, the expected pipeline rerouting will be scheduled in the month of February - March, 2017 for about 5 weeks,

Further updates in this regard will be provided when the actual shutdown of the Haldia Plant for the above purpose is undertaken in February and March, 2017.
 