Exchange Disseminated Time 18/07/2016 13:19:03 | NHPC Ltd has informed BSE that consequent upon successful trial run of Unit No.# 3 of Teesta Low Dam HE Project Stage IV (4 x 40 MW) at its installed capacity of 40 MW for continuous 12 hours on dated July 12, 2016, the unit No. #3 is hereby declared under commercial operation w.e.f. 00:00 hours of July 17, 2016.
Further, 100% Power generated from TLDP-IV has been allocated to the state of West Bengal and the same shall be supplied through West Bengal State Electricity Distribution Company Limited (WBSEDCL). |
|
|