Exchange Disseminated Time | With reference to the earlier letter dated August 04, 2014 regarding the Board of Directors at its meeting held on August 04, 2014 had approved setting up of another specialty chemical plant at SRF's Chemical Complex in Dahej, Gujarat, at an approximate cost of Rs. 113 Crores.
SRF Ltd has now informed BSE that Phase I of the aforesaid project being production of first batch of the product (P17A) of the desirable quality has been achieved. Accordingly, this is to report that Phase I of the project has been commissioned on March 27, 2015 at a cost of Rs. 63 Crores which has been capitalized. |
|
|